- 3 min reading
International School Utrecht had outgrown its buildings. While the school waited for its new permanent campus at Utrecht Science Park, the municipality needed a temporary solution that could give students and staff enough space for everyday school life.
Adapteo was selected to deliver a temporary school building of up to 8,700 square metres at the Papendorp business park on Van Deventerlaan. The building had to be delivered quickly, work for students aged 4 to 18, and support a school community that had grown dramatically in just over a decade.
A steady increase in students
We desperately needed space and kept expanding: first giving up another piece of the schoolyard for modular classrooms, then adding another building,"
says Marieke Folkers, Director of ISU.
In eleven years, ISU grew from 64 students to 1,120. Today, the school has 165 employees and is expected to grow further, to around 1,200 students.
“Utrecht’s international business environment is growing, and the city wants to attract more international companies,” says Marieke. “Before employees choose a house or sign a contract, they arrange a school for their children. At our previous location, we joked that we would end up taking over the whole street, because in the end we had four buildings on the same street.”

Inquiry-based learning needs room
ISU teaches students aged 4 to 18 through inquiry-based learning, an important part of the International Baccalaureate programme. Students are actively involved in their own education and school community, with room to make choices, ask questions and explore ideas.
That way of learning needs space: for movement, group work, independent study and different activities throughout the day. It also meant that the municipality of Utrecht had to think creatively about how to support the school until the new permanent building is ready.
“For temporary locations, we first look at existing buildings that we can convert,” says Merel Geurts, Project Manager on behalf of the municipality of Utrecht. “But because of the laws and regulations that apply to schools, that can be difficult. Modular construction was the solution, because it can be realised quickly and affordably. The circular aspect was important to us too: after its temporary use, the building can be reused for another purpose, in another place.”

The design was a pleasant surprise
In the tender, the municipality gave contractors room to propose their own solutions. That made the process both practical and open-ended: the municipality knew what the school needed, but not exactly what the best solution would look like.
“In the tender, we gave the contractors quite a bit of freedom, so we were curious to see what they would come back with,” says Merel. “Adapteo offered the best design for the best price, scored well on circularity and was able to deliver it quickly, within one year.”
“The speed of construction was insane,” says Marieke. “From drawing to building in just a few months. You hope that what you come up with will work, and it did. One big plus with Adapteo was that the corridors could be five centimeters higher, which makes the building feel more spacious.”

Light, space and a central meeting point
The lower and upper school are each located on one side of the building and come together in a large open auditorium in the middle. The ceiling in the auditorium reaches up to the second floor, giving the entrance area a bright and spacious feel.
The auditorium has quickly become an important part of the school. Students use it during breaks and free periods, and the school also uses it for parents’ evenings, teaching activities and as a space with a grandstand function.
“It feels big, light and spacious when you come in, and that gives a very pleasant first impression,” says Marieke. “Because the building has two floors, you get twice as much daylight. Modular construction has existed for more than 65 years? I’m curious to see what else will be possible in the future. The whole building is really nice — all the pleasures of a new building: spacious, light, clean and bright.”
Learning from the building before the next move
Moving into a new school building is always a bit of a puzzle. It is not only about the number of classrooms, but about how daily school life actually works: which way a door should open, where certain activities should take place, and how different spaces relate to each other.
A few practical lessons appeared once the building was in use. Drama lessons above an office turned out to be less than ideal, and a secluded toilet area became something to rethink. For ISU, these discoveries have been useful preparation for the next move.
Marieke sees the process as a valuable learning experience:
A perfect dress rehearsal for when we move to our permanent building!”