- 2 min reading
Tångvallaskolan needed a fully functioning temporary school
When Tångvallaskolan in Vellinge Municipality in Sweden was affected by moisture and mold damage, the municipality needed a solution that could keep everyday school life running while a new school was being built. For around 450 students, that solution became a modular school from Adapteo.
“It’s not a small school. We have about 450 students here with an on-site commercial kitchen, dining hall, and after-school care. We have also built a sports hall next to it. It is a fully functioning school.”
– Robert Seremet, Project Manager at Vellinge Municipality
Tångvallaskolan is an F–9 school that was inaugurated in 1979. Like many buildings from the same period, it had long struggled with moisture and mold issues.
“The construction methods used at the time were considered excellent, but it has now become clear that they weren’t so good after all. Quite a few municipalities in the area have had problems specifically with 1970s-era buildings, due to design flaws,” said Robert Seremet.
A common problem in 1970s buildings
The problems at Tångvallaskolan were not unique. Across Sweden, many buildings from the 1970s have faced similar issues, often linkedin to moisture poor ventilation and construction methods that later proved problematic. By the 1980s, the term “sick building syndrome” had become widely used to describe health problems connected to indoor environments. Since then, municipalities worked to refurbish or demolish affected structures.
After several years of attempted renovations, Vellinge Property Committee decided in 2021 that the old school building should be demolished. Construction of the new Tångvallaskolan began shortly afterwards, with completion expected in 2026. The new school will also make use of materials and equipment from the old building where possible.
“The idea is to use whatever we can for the new school, primarily the bricks. And much of the equipment will also be moved to the new school eventually,” said Robert Seremet.
Six months from procurement to opening
The new construction period created an urgent need for temporary teaching spaces for both students and staff. Vellinge Municipality therefore started a procurement process through SKR for a modular school solution. Three suppliers submitted tenders, and Adapteo was selected.
In January 2023, around six months after procurement, the modular school was ready to open.


Large-scale success
In total, Adapteo delivered 199 modules to Tångvallaskolan. The modular school includes classrooms, science labs, craft rooms, a dining hall, a commercial kitchen and after-school facilities.
“The result turned out very well, and staff and students were pleasantly surprised when we were there for the opening day,” said Carl-Magnus Strandberg, Head of Sales at Adapteo Sweden.
Would you like to speak with a sales representative or learn more about how we can create a modular building together? Adapteo works with municipalities and schools to create flexible learning environments that match each project’s needs.