The project got off to a challenging start. The procurement of a temporary school could not occur until planning permission was granted, which meant that the timeframe would be very tight. This raised concerns that the municipality would be without a tender, but the needs turned out to be met by Adapteo. “They should be commended for the fact that they had the power to take on the assignment with such a tight schedule”, says Sandra Davidsson, construction project manager at Nacka Municipality.
Another challenge in the project was to get enough power to the land area, which required extensive logistics work. At the same time, other construction projects have also been underway in Älta that need a lot of co-planning and coordination from the municipality. With the adaptability of both the municipality and contractors, craftsmen and suppliers, the project could proceed one step at a time.
“Everyone has been very solution-oriented and adaptable to reality,” says Sandra Davidsson.